Post by lauraandmatt on Aug 24, 2015 20:51:57 GMT
Hi I am just wondering if anybody else has had any problems with Harron and dates, we reserved a Hanley in March and was told our original move in date was 31/07 after several push backs we are now on 02/10. Has any body else experienced this problem, we have also found we never get a reasonable explanation why, I get that there are always problems with new builds but to me Harron don't seem to mind upsetting us.
|
|
rocky
New Member
Posts: 17
|
Post by rocky on Aug 24, 2015 21:38:48 GMT
We are having the same problem. Just had a call today to tell us that the completion date for our apartment has also been put back to 2 Oct. Building work on the block of which we are in the middle seems to go through phases where very little progress seems evident . For several weeks now we have had windows fitted on the first floor level but still no sign of any windows being fitted to the second floor.
|
|
|
Post by lauraandmatt on Aug 25, 2015 7:11:46 GMT
We are the first Hanley, It's an absolute joke, and we can't even get it fixed which is no help to us as we need to give 30days notice, Harron don't seem to really care about the extra costs to us now they have our money ha. Just want to move.
|
|
|
Post by alison on Aug 26, 2015 7:03:02 GMT
They were working in your house yesterday Laura. The plasterer was there for several hours and worked right up to the downstairs window. No window in there yet though.
|
|
|
Post by lauraandmatt on Aug 26, 2015 7:45:19 GMT
Oh brilliant thank you, hopefully they will get a move on. Need to get down there and crack the whip ha.
|
|
ann
New Member
Posts: 36
|
Post by ann on Aug 26, 2015 9:57:06 GMT
We had the same problem with Barratts. Original completion date given as January 2015, kept getting put back, without explanation. Finally completed 31st April 2015!
|
|
|
Post by lauraandmatt on Sept 7, 2015 14:41:04 GMT
Yet another fantastic call from Harron, our move in date is now 16th October!
|
|
Deleted
Deleted Member
Posts: 0
|
Post by Deleted on Sept 7, 2015 16:28:08 GMT
Hi Laura, Have they given you any reasons why? We are around the corner from you supposed to move in December. Jessica
|
|
rocky
New Member
Posts: 17
|
Post by rocky on Sept 7, 2015 21:14:28 GMT
We had a similar call today. Apparently Harron are now saying they don't expect to finish working on our apartment until 9 Oct meaning we won't be expecting to move in until at least 23 Oct , a further 3 weeks from what we were told previous. Reason given for delay was something about traders not providing materials / services as quickly as expected !!
|
|
|
Post by lauraandmatt on Sept 7, 2015 21:16:32 GMT
Apparently something to do with materials, always some sort of excuse,
|
|